Active Project


Project Management Project risk management Public New

Easy  

7min

A company currently has three active projects:

  • Project A has a 85% chance of a 230,000 USD profit and a 15% chance of a 230,000 USD loss.
  • Project B has a 55% chance of a 900,000 USD profit and a 45% chance of a 900,000 USD loss.
  • Project C has a 73% chance of a 300,000 USD profit and a 27% chance of a 250,000 USD loss.

Which project has the highest monetary value, and what is the amount?

Project A, 161,000 USD.
Project B, 495,000 USD.
Project C, 219,000 USD.
Project C, 151,500 USD.
Project B, 900,000 USD.
Project A, 460,000 USD.